Season notes
A restaurant furniture ordering timeline, counted backward from opening day
The first warm Saturday won't wait for a truck. Between the afternoon you pick the chairs and the morning a driver pulls up to your curb sit a handful of waits, and most owners count only one of them: the lead time.
Count them all. This piece walks a patio opening backward from the day the doors open, using the figures our process runs on, and ends with a worked schedule so you can see where twelve weeks goes. Two words carry the weight here, estimate and promise. Most of what follows is an estimate, and it is better planned that way.
Open diagram at full size (new tab) ↗
Count back from the day setup must finish
Opening day is the wrong end of the string. Pull from the day the last chair has to be standing on the patio, a day or two earlier, because someone has to unpack, assemble, place and walk the room. Say that day is the Thursday before the Saturday.
The waits run in this order, from your first look at the outdoor furniture to the last screw:
- Swatches: expect our email acknowledgement within a business day. UPS Ground transit normally takes two or three business days after dispatch.
- The order: a person reads every order and answers within one business day, and nothing is charged when you submit.
- Payment: an invoice follows the review and the freight confirmation. Standard purchases need full payment before they ship. For custom furniture, 40% starts the order and the unpaid amount falls due ahead of delivery.
- Lead time: allow 14 to 21 business days on standard items. Custom work can reach about eight weeks.
- Transit: added on top of the lead time, and an estimate.
- Setup: unloading, unpacking, assembly and placing belong to your crew.
Four of those six come with a figure. Transit comes with the freight quote for each address, and setup comes from how many hands you have on the day.
Estimate versus promise
The lead time is a range, so plan to the long end of it. Transit is an estimate from the freight quote, and it gives you a number to plan with, never a date to stake the opening on. Leave a payment window on the calendar and confirm when funds must arrive for your particular order.
Once confirmed, an altered quantity, finish, or delivery arrangement requires agreement in writing. Ask about any new freight or restocking costs at that point. A custom line in production can't be changed at all. The cheapest moment to change your mind is the one before you press submit.
Twelve weeks, line by line
Say you have 12 weeks, which is 60 business days, between today and the day setup ends. The patio needs 60 chairs and 15 tables, which is 75 pieces and well past the minimum of 8. Whether you build it from chairs, tables or the taller bar stools, remember that a line is one configuration. A solid-back resin chair in black and in sand is two lines even though it is one model, and a black aluminum table set with an umbrella base in two sizes is two more.
Now the days. Swatches take 4 to arrive, one to confirm and three in transit, and you want 3 more to look at them where guests will sit: 7. Finishing the plan and submitting takes 2, the review takes 1, and say 3 for a check or wire to settle. Standard lead time at the long end is 21. Say the freight quote reads 5 days of transit, and give your crew 2 days of setup.
Add them: 7 plus 2 plus 1 plus 3 plus 21 plus 5 plus 2 makes 41. Sixty minus 41 leaves 19 business days of cushion, nearly four weeks. Comfortable.
Now make one line custom, an upholstery outside the listed options, and plan around its long end. About 8 weeks is 40 business days, so the sum becomes 7 plus 2 plus 1 plus 3 plus 40 plus 5 plus 2, which is 60. The cushion is gone, and every other wait now runs late the day it runs long. That is the rule of thumb in one example: add up the long ends, then keep a week that nobody touches.
The truck is part of the timeline
The standard freight handover is at the business dock or truck tailgate, with the furniture on pallets. Moving it from the curb to the patio is on your crew. Tell us at submission if the destination needs a liftgate, indoor handover, residential service, or limited-access arrangements. Those services add a charge. Carrying goods on stairs remains outside the driver's work. A patio two flights up, or a roof, needs a plan before it needs a truck, and our pieces on freight costs and rooftop orders take that apart.
A large purchase may arrive in separate loads. Give each arrival its own receiving team and allow about 30 minutes for unloading. Compare the carton and pallet totals with the delivery paperwork, examine their condition, and record damage or shortages before signing. Use "subject to inspection" when a complete examination cannot be finished there. The delivery page holds the whole routine.
Two slips that eat the cushion
One is treating transit as a date. The quote's number is a good guess, so use it, but let it live inside the cushion and never on the opening day itself.
Another is picking colors late. Finish and upholstery lists change over time, and an addition to a room you already have needs a fresh swatch and a confirmed color before you order. A guess found on a pallet hurts most on a custom line, since those can't be cancelled or returned once confirmed. The budget planning guide shows what a change costs on the money side.
The Monday that starts the count
Pick the day setup must finish, count back with the long ends, and circle the Monday you land on. That Monday starts the swatches, not the order. If it is already behind you, the plan changes shape: fewer custom lines, standard pieces where you had hoped for special ones, and a conversation with a specialist about what can still land.
Then do the one thing you can do this afternoon. Open the samples page, request swatches for the finishes you are weighing, and save the chairs and tables to a patio plan with the setup date in the notes. The how to order page takes you through the rest, and put the sample confirmation beside the opening calendar.